Home / Progetti / Produzione di energia / Survey and design of China’s first pumped-storage power station in a complex karst area – Caiziba pumped-storage power station in Fengjie, Chongqing

Progetto

Nome dell'organizzazione e ragione sociale

Shanghai Investigation, Design & Research Institute Co., Ltd.

Survey and design of China’s first pumped-storage power station in a complex karst area – Caiziba pumped-storage power station in Fengjie, Chongqing

Image Credit: Shanghai Investigation, Design & Research Institute Co., Ltd.
Un cerchio nero con una "B" bianca sopra le parole "Finalist 2025", in riferimento a YII 2025, su sfondo bianco con una barra arancione in alto.
A badge with an orange top border displays the text "Finalist YII 2025" on a white background, highlighting recognition for outstanding 2025 projects.

Progetto

Nome dell'organizzazione e ragione sociale

Shanghai Investigation, Design & Research Institute Co., Ltd.

Survey and design of China’s first pumped-storage power station in a complex karst area – Caiziba pumped-storage power station in Fengjie, Chongqing

Image Credit: Shanghai Investigation, Design & Research Institute Co., Ltd.
Categorie Awards

Produzione di energia

Luogo

Fengjie County, Chongqing City, China

Software Bentley utilizzati

Bentley Descartes, Bentley LumenRT, MicroStation, OpenPlant, PLAXIS, ProjectWise, STAAD, SYNCHRO

Sintesi del progetto

The Caiziba pumped-storage power station is the first large-scale pumped storage project in China’s complex karst area. Located amid extensive karst formations, including caves and fissures, the project presented significant site challenges, compounded by technical and coordination issues. Previous traditional design and modeling applications resulted in data fragmentation and workflow bottlenecks. To address these shortcomings, the project team realized that they needed an integrated, dynamic technology solution.

Leveraging Bentley’s 3D modeling, digital twin, and construction simulation technology, the team established a collaborative digital platform and standardized component library, streamlining workflows and achieving dynamic coupling of geological modeling and construction. Working in a coordinated design environment eliminated 1,850 conflicts to avoid rework costs of approximately CNY 4.5 million. The integrated digital twin solution shortened the construction period by 42 days and optimized steel and concrete usage, reducing carbon emissions by 11,110 tons to deliver intelligent green infrastructure that supports regional clean energy transformation.

20% di sconto sui software di Bentley

L'offerta termina venerdì

Usa il codice coupon "THANKS24"

Celebra l'eccellenza nella delivery e nelle prestazioni delle infrastrutture

Year in Infrastructure e Going Digital Awards 2024

Candida un progetto per i premi più prestigiosi nel settore delle infrastrutture! La scadenza per la partecipazione è stata prorogata al 29 aprile.