米兰新建的标志性 ENI 总部大楼将成为世界上最具创新性的可持续发展项目之一,包含三座相互连接的办公楼、一座标志性的天桥和 11684 平方米的总绿化面积。Webuild 接受委托在有限的场地和期限内交付项目,整个施工计划的关键节点是大型钢结构天桥,其装配十分复杂。为了确保项目按计划进行并确保安全、简化的工作流,Webuild 需要协同式数字化施工模拟解决方案。Webuild selected SYNCHRO to establish a dynamic, virtual construction environment and a digital twin to evaluate multiple scenarios, perform clash detection, and determine a construction solution that optimized planning and safety while minimizing social and environmental impact. Bentley’s 4D construction technology reduced rework by 90% and the construction schedule from 85 days to just four days. Working in a connected digital platform optimized site layout, decreasing the carbon footprint of the project by 30%, and provided insight into all phases of construction, achieving zero on-site accidents.