Application of GIS+BIM digital intelligence technology to the entire lifecycle of China Southern Power Grid’s Guangxi Nanning 500kV power transmission and transformation project

Image Credit: China Energy Engineering Group Guangxi Electric Power Design Institute Co., Ltd.
A black circle with a white "B" above the words "Finalist 2025," referencing YII 2025, on a white background with an orange bar at the top.
A badge with an orange top border displays the text "Finalist YII 2025" on a white background, highlighting recognition for outstanding 2025 projects.

项目

组织和公司名称

China Energy Engineering Group Guangxi Electric Power Design Institute Co., Ltd.

Application of GIS+BIM digital intelligence technology to the entire lifecycle of China Southern Power Grid’s Guangxi Nanning 500kV power transmission and transformation project

Image Credit: China Energy Engineering Group Guangxi Electric Power Design Institute Co., Ltd.
奖项类别

能源输送和通信网络

地点

Nanning City, Guangxi Zhuang Autonomous Region, China

使用的 Bentley 软件

Bentley LumenRT, MicroStation, OpenRoads, OpenUtilities, ProjectWise, ProStructures, SYNCHRO, Other (OBD)

项目概要

This 500-kilovolt power transmission station aims to optimize Nanning City’s power grid structure, improving power supply reliability and promoting clean energy. Located in a hilly area, the project presented site challenges compounded by coordinating multiple disciplines and substation equipment. To address these issues while achieving full clean energy consumption, the company sought to establish intelligent digital workflows and substation processes. When traditional technology methods proved ineffective, the company used this project as an opportunity to improve current digital design standards in China’s power sector.

Leveraging Bentley Open applications, ProjectWise, and SYNCHRO, the company established a collaborative BIM design platform and performed construction simulation. Working in a connected digital environment streamlined workflows to shorten design time by 10% and resolve 85 design collisions that reduced on-site construction changes by 91.8%. Through accurate 3D modeling, the team reduced the construction period by 5%. The 3D models provide comprehensive data and support for intelligent, digital power grid operations and maintenance.